Installation of interconnector between Scotland and island of Hoy

The Pentland Firth sea route runs between the Scottish mainland and the Orkney island of Hoy. This is where, in the summer of 2023, we installed a 33 kV interconnector cable to ensure energy supplies to the Orkney Islands group. The new connection considerably strengthens the local distribution grid.

On behalf of Scottish and Southern Electricity Networks (SSEN), we supplied and installed an interconnector cable between the Scottish mainland and the Orkney Islands group between April and August 2023. A challenging project, both due to the client’s tight timeline and the difficult soil conditions and strong currents that characterise the strait.

We took on the installation and protection of the cable and outsourced the fabrication and transport to cable manufacturer Ningbo Orient Cable.